Home  >>  Investor Relations  >>  Prasarana Denies Blocking Bumi Firms in MRT Project

 

 
 

 

Prasarana Denies Blocking Bumi Firms in MRT Project

 
   

KUALA LUMPUR, April 23 — The owner of the Klang Valley Mass Rapid Transit (MRT) project has rejected claims that Bumiputera contractors are being denied opportunities in the construction of Malaysia’s largest infrastructure project.

Syarikat Prasarana Negara Berhad (SPNB) group managing director Shahril Mokhtar responded to Perkasa’s claims by insisting equal chances were offered to all firms to bid for contracts under the multibillion ringgit rail project provided they meet the regulatory guidelines set by the government.

“Prasarana is confident that the local market has a pool of genuine, competent and suitably qualified Bumi and non-Bumi contractors. “The pre-qualification (PQ) criteria are not overly stringent and enable many experienced contractors to qualify on their own without entering into a joint venture with others,” Shahril said in a statement.


He said the guidelines, which include pre-qualification criteria and selection of the contractors for the work packages, were to ensure that only “genuine, competent and suitably qualified” contractors who are able to meet the project’s deadline are selected. Malay rights group Perkasa and other NGOs representing Bumiputera entrepreneurs complained on Thursday that the project’s “strict” guidelines effectively disallowed Bumiputera participation and only benefited the “rich non-Bumis”.

Speaking on behalf of the group, Perkasa economic director Dr Zubir Harun said the construction packages for the MRT were being “looted and monopolised” by MMC-Gamuda, the appointed project delivery partner (PDP) for the rail system. He said Prasarana had on March 30 imposed additional criteria on contractors bidding for the project, making it virtually impossible for Bumiputera participation.

The criteria, according to Zubir, were:

• contractors taking part in the project tender are forbidden from forming joint ventures or consortiums;

• companies of contractors are forbidden from forming any joint ventures with foreign companies in the tender of the project;

• the formation of a consortium of two or more companies is strictly forbidden;

• bond payment of RM300,000 required at the pre-qualification level.

But Shahril brushed these concerns aside, claiming Zubir’s statements were a case for misrepresentation. He explained that the guidelines had to be imposed as the size and complexity of the estimated RM36.6 billion rail project, Malaysia’s most expensive construction project to date, carries with it risks of delays and cost overruns. “As such it is crucial that the contractors selected must possess the expertise and financial strength to undertake a project of this magnitude,” he said.

Shahril added that Prasarana had also extended invitations to both non-Bumiputera and Bumiputera contractors to participate in the tender process and that the criteria set out in March had two categories — Open category and Bumiputera category. He also disputed Zubir’s claim that Bumiputera contractors were unable to raise the RM300,000 tender bond required without entering into a joint venture, pointing out that the major work packages were targeted towards companies that have the financial strength to raise the sum.

“Prasarana is also aware that there are Bumiputera contractors who cannot meet the criteria for the main work packages but are qualified to participate in the subcontract work. “Therefore smaller contractors will have opportunities and roles to play in the MRT project at a level that commensurates with their skills and experience. They will not be excluded from this project,” he said.

The total project cost of the MRT was estimated at RM36.6 billion for three rail lines through the Klang Valley when it was first proposed two years ago but that projection did not include cost of land and also rolling stock for the MRT. SPNB has also not finalised the financing and project manager’s fees for the MRT although planning has started for initial civil engineering work to begin in November.

Regulator Land Public Transport Commission (SPAD) had said the Finance Ministry has set up a special purpose vehicle (SPV) to raise funds for the project but had admitted the method has yet to be determined. The SPNB chief had also said some 100 firms have applied for pre-qualification for the 16 packages in the elevated part of the 51km-long MRT; the deadline for pre-qualification ended on April 13.
 

Disclaimer: Such news and article is a verbatim copy from other websites and is solely for the purpose of providing general information about the proposed KL MRT, it may be changed by the Project Owner of the KL MRT at any time and must not be relied upon in connection with any investment decision. The website owner should not be held liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein.
 

 
| HomeAbout us | Contact us | Disclaimer |                 

Copyright © 2011 - 2013 All Rights Reserved